Mwinilunga, which recently attracted public attention following the discovery of notable gold deposits at Kasenseli has historically been known as the home of pineapples in Zambia.

And when we reported that the a brand new fruit processing plant is erected to revive the industrial uptake and processing of pineapples and other fruits, there was doubt as to weather construction of this new plant has even started.

The Zambian Business Times – ZBT can exclusively confirm that the construction of the warehousing infrastructure has advanced and that the fruit processing plant has already been built and will be delivered from India to Mwinilunga.

Three governments institutions namely Industrial Development Corporation (IDC), Workers Compensation Fund Control Board (WCFCB) and the National Pensions Scheme Authority (NAPSA) have joined hands to build the Kalene fruit processing plant by initially investing about K100 million (about US$5.5 million).

Project manager for the construction of the Kalene Fruit Processing plant in Mwinilunga, Dr. Charles Chifunda, confirmed to the Zambian Business Times – ZBT that the construction of the warehousing and offices will be completed in October 2020 and the launch of the Fruit processing plant will be in December 2020.

Dr. Chifunda told ZBT that the plant has already been built in India and that has plant parts and equipment is on its way. The logistics have been put in place to ensure that the equipment arrives when the site and warehouses are ready,

“The equipment has not yet come in, but it’s already manufactured. Coming in of the equipment has been timed with the construction of the office buildings and warehouse. Because we don’t want it to come in and it stays outside. So we are synchronizing the construction with the bringing in of the equipment”, he told ZBT.

Furthermore Dr. Chifunda said that the warehouse building is approximately 5,000 square meters and somewhere in October the building will be done and this in return will mean the equipment will arrive after that, which will be followed by installation, testing and then production will resume.

The building is about 5,000 square meters. So the whole idea is in about October 2020, the building will be done and about that same time the factory equipment will be in the country straight into the structure; and we start the assembling, testing and then proceed to hand over for the management to kick start production.

Mwinilunga already has an active pineapple farming community, so the inputs will be readily available. But IDC has stated that an out-grower scheme has been put in place to ensure consistent supply of the fruits that will be used for the fruit processing plant.

The plant is going to be imported from India. The company to run the Kalene Fruit Processing Plant is already formed. The initial fruits to be processed by the plant is Pineapple and tomato, but the plant is scalable to process other fruits.